Starship Development Thread #47
LettuceTurnipTheBeet @ LettuceTurnipTheBeet @lemm.ee Posts 19Comments 133Joined 2 yr. ago
So B9 is at the OLM ready to be lifted. Wonder if they’ll do so today or just let it stand there.
New comment from /u/santacfan on Reddit:
Starbase live-
10:52pm- More rebar to the pit
1:46am- Something was tested on the OLM
2:34am- Yep more rebar. (Pretty quiet night except for work in the pit)
3:08am- More rebar into the pit. Long reach excavator appears done with the concrete
4:17am- Forklift brings a generator over to the pit area
4:19- B9 rolls down Remidos to Hwy 4
4:55am- Rebar work continues around the deluge pipe pit in the cryo leg area
6:14am- Forklift brings in a new light tower and blinds view under the OLM
6:29am- B9 starts rolling
7:29am- B9 turns into the launch site
7:42am- A giant rocket rolling in isn’t going to stop the rebar work
7:45am- B9 arrives at the pad
7:54am- Chopsticks start rising
7:59am- Chopsticks open
8:12am- Booster moves closer to lift area
8:24am- Chopsticks lower into lift position
8:31am- More rebar lifted over
8:50am- B9 moves in between chopsticks
9:06am- Basket lifted up to the top of the OLM
9:30am- Basket lowered
9:36am- Square Piece of equipment lifted off the top
9:41am- Piece of equipment lifted out of the pit
9:45am- More rebar lifted over
10:18am- More rebar. They’re really pushing on it today
10:29am- Yep another batch of rebar. The next concrete pour has to be coming soon
10:56am- Crane moves to right side of the OLM and lifts a rebar cage structure. Moves it over by the new stairs. I’d assume just staging for later. Then crane moves back to left side.
11:21am- Rebar
11:23am- PA announcement- Overhead drone work
12:05pm- Workers up at the base of B9
12:15pm- Pad clearing
12:23pm- Chopsticks closing around B9
12:28pm- Closing in tighter to latch on
12:33pm- Starting to raise up to the pins
12:54pm- Sounds like the drone that warned Jack the other day is out warning people again today
1:03pm- Ship 28 moves to the entrance of the high bay
1:37pm- Clamps on the stand retracting from booster
2:02pm- LR11000 lowering at the build site. Most likely being reconfigured to finish building the new mega bay
2:06pm- One of the tall aerial work platforms arrives at the launch site
2:10pm- Workers climbing on to the stand
2:18pm- (14:18) Rover 2- Sounds like somebody’s radio by the camera. Lift will be attempted again in 2 hours.
2:20pm- Looks like some of the clamps are stuck?
2:23pm- Aerial work platform goes up to the top of the booster
2:30pm- Workers climbing on top of B9
2:46pm- When you got some unexpected free time, you grab a broom and try to get rid of some of that dust
3:00pm- Aerial work platform comes down
3:27pm- Workers back on top of the OLM
3:58pm- Workers climbing off B9’s stand. Finally unstuck?
4:02pm- Ship 28 lifted in the high bay
4:08pm- Pad clearing again. Looks like 5 people still working on the booster
5:30pm- Stabilizer arms going in
5:48pm- One guy still walking around on the stand
6:31pm- People are back on top of the OLM. Not looking good for the lift. The stand appears to be afraid to let B9 go after seeing what happened to B7.
8:10pm- It moved!!!
8:11pm- S28 unhooked from the bridge crane
8:17pm- Clamps releasing
8:27pm- Clears the stand
8:34pm- Stabilizer arms going in once again
8:37pm- Drone up
8:54pm- Guide pins retract back into the stand
8:55pm- Up we go at a good pace and then it paused
9:00pm- That SpaceX drone has quite the spotlight
9:04pm- Booster is rotating
9:06pm- Going up again
9:09pm- Clears the OLM. Pauses. Drone checking underside of the booster
9:11pm- Starts rotating over the pad
9:18pm- Starting to lower
9:27pm- Engines starts going below the lip of the OLM
9:32pm- Drone checking out one of the skates on the right side of the chopsticks
9:45pm- Engines below the lip of the OLM. Making final adjustments
Rover 1-
16:47- New puck shucker is rolled in under Ship 28
17:05- S28 touches down on stand
(This gets synced)
New comment from /u/santacfan on Reddit:
Starbase Llive-
3:13am- Work starts back up
4:31am- Crane picks up a light tower from in front of the OLM and swings it over to the pit on the left side
5:08am- They are using the long reach excavators bucket to move concrete from a delivery truck to the gaps between the legs and the manifolds
5:12am- Crane swings a load of long straight rebar over to the pit
5:32am- Crane swings another load of rebar over to the pit
6:49am- Final segment of the 4th level of the new mega bay is lifted
7:45am- More rebar lifted over to the pit
8:08am- Another load of rebar, looks like one more load sitting there waiting.
8:23am- Workers carrying sticks of rebar over to the area between the cryo pit lid and the OLM. Other workers appear to be getting more of the gaps between the legs and manifolds ready for concrete
9:23am- Load of rebar lifted to the pit
9:38am- Pump truck goes up by the new cryo pit
9:40am- Crane lifts a big ball of what looks like twisted metal out of the pit. Ghost of SN11?
10:24am- Workers up at the SQD
10:58am- More rebar lifted over
11:04am- Yep you guessed it, more rebar
11:31am- Even more rebar. (When we saw the wire mesh mats lifted over yesterday, I thought they were close to done. I was wrong)
1:34pm- Rebar magically continues to appear out of no where. (Okay it was probably just a new delivery )
1:36pm- Worker on top of the chopsticks looking at the rail
2:23pm- Crane lifts black object over to the pit
4:04pm- Pump truck folds up
4:22pm- Crane lifts a load of supplies off of the top of the OLM
4:35pm- Crane lifts another load off the top
4:38pm- More rebar lifted over to the pit
4:56pm- 3rd load off the top of the OLM. (Maybe the scaffolding out of the center? There are people climbing around on the scaffolding on the top but it doesn’t look like they are actually taking anything apart)
6:10pm- Lift up looking at the cameras at the end of the stabilizer arms
7:19pm- Second crane comes in and lifts what looks to be a new dog house and sits it off to the side. Looks longer like the one for the cryo leg.
7:44pm- Second crane leaves. Doesn’t look like it’s going to install the new doghouse
8:55pm- 2 people back up working on the SQD
9:00pm- Gravel being dumped over by the pit on the left side. Just outside of the form work.
9:10pm- Long reach excavator returns. Looks like it’s dumping concrete between the legs and manifolds again.
9:25pm- Definitely doesn’t look like they are preparing for any testing tonight.
9:45pm- I may have spoke to soon. Pad starting to clear out some. There are still people welding, grinding, and people over in the pit though
10:14pm- More rebar lifted into the pit
(This gets synced)
New comment from /u/santacfan on Reddit:
Starbase Llive-
1:15am- Scaffolding on the cryo pipe leg starting to get disassembled
1:27am- Forklift brings rebar over to the left side pit
1:30am- long reach excavator arrives right side of the OLM
1:59am- Excavator starts digging on the back side of the OLM
2:58am- Crane lifts rebar to the back side of the OLM
4:17am- Forklift brings more rebar to the left side pit
4:35am- B9 goes on a walk to the rocket garden
4:43am- Crane lifts more rebar to the backside of the OLM
7:37am- Long reach excavator leaves
8:16am- fixing the silt fence around the left side of the OLM
10:58am- Group of engineers/bosses surveying things
11:32am- Forklift lifted 2 loads out of left side pit. Lift was blocking what they were though
11:36am- Crane lifts load of straight rebar over to the left side pit
11:50am- Lots of lifts going up and down to the top of the OLM all morning. Welders still working under the OLM. Excavators still digging over by the left side pit. Lift up at the LOX tank of S25.
12:38pm- Lift goes up to the top left skate on the chopsticks. Hopefully with some really good grease
1:04pm- Box lifted off the top of the OLM by the crane
1:51pm- BQD hood is getting painted
2:13pm- Scaffolding being removed that went to the door on the right side of the OLM
3:29pm- Wire mesh mats lifted over to the pit on the left
4:05pm- They made pretty quick work of the scaffolding on the right side
4:16pm- Lift goes up to the left chopsticks stabilizer arm
4:42pm- Forklift brings in a load of rebar and drops it off at the dirt berm leading up to the front edge of the pad.
4:52pm- More rebar brought over
7:57pm- Pad clear announcement (Can be heard better on Rover 2)
8:05pm- They don’t appear to be removing all the equipment like yesterday
8:12pm- B10 getting frosty at Massey’s. (Raptor Roost caught it one minute earlier at 8:11. Both tanks already had frost)
8:32pm- Frost receding
8:48pm- Something is rolling towards Starbase from Masseys
8:50pm- Sheriff at the launch site entrance
8:58pm- Big vent at the OTF. (Are we redoing the test from the other night but with a full closure just in case?)
9:05pm- It’s the new puck shucker being moved from Masseys
9:39pm- OLM and OLT venting
9:43pm- FireX
9:49pm- New water nozzles around the underside of the OLM?
10:21pm- Depress vent from the OLT and OLM
10:39pm- Workers to the pad. Road still closed
11:03pm- Workers leaving the pad
11:15pm- Venting picking up again
11:20pm- Venting starts dying off
11:50pm- Picking up again
11:55pm- Dies off again (Just testing the valve over and over?)
12:04am- Cars back to the pad
12:09am- The cars aren’t keeping the venting from increasing again
12:12am- Pope stack
12:20am- Dies off again
12:45am- Bunch of cars to the pad. Road open.
(This gets synced)
Booster 9 has been moved to the rocket garden.
https://twitter.com/nasaspaceflight/status/1681282819014705152
I wonder what that means for the next launch. Booster readiness seems like one of the top remaining items now, with the booster needing the hot stage ring for the ship to fit now. Will they do fit tests / static fires first? Or maybe prepare a different booster with the extra ring?
One other approach could be that the extra ring “clips on” the existing staging hardware. Would mean that no changes to the booster are necessary, and if they later decide not to risk hot staging they could possibly do a traditional staging approach, leaving the ring attached to the ship instead? Sounds pretty crazy but you never know.
Wel heel vervelend voor mensen die zo’n fiets hebben.
Heb zelf een RadPower fiets en die gaan ook weg uit Europa. Maar die fiets heeft ook nog eens banden die nergens anders te krijgen zijn..
En ondertussen is dat bedrijf nog aan het stunten met aanbiedingen.
And indeed already out of date, since the deluge system has undergone its first tests already!
https://twitter.com/nasaspaceflight/status/1681007026556502016?s=46&t=Mj914Aam14loAYQOISZ9zQ
Wow! Didn’t expect them to test so soon!
Wonder what the next steps are, for some reason I expected this to be more violent.
New comment from /u/santacfan on Reddit:
Starbase live-
11:15pm- Lift moves in to where crane was parked
1:55am- 3rd piece of shielding goes up to the draw works shed
3:06am- Pump truck folds up and leaves
6:39am- Vent hose being installed in the new door on the OLM
7:29am- Pump truck going up to the left of the OLM. Extends over to the new engine chill dump pit
7:51am- Second vent hose being installed
8:51am- Tower cladding piece lifted
9:15am- Second cladding piece lifted (They look like old pieces that they may have fixed)
10:06am- Crane is back in its position in front of the OLM
10:14am- 3rd cladding piece lifted
10:20am- Grover is leaving the launch site
10:37am- Basket goes into the middle of the OLM
10:47am- Pump truck folds up
10:58am- Lifts back up at the methane tank on S25 (I wonder what they are doing in there)
11:11am- An overflowing basket is removed
11:14am- Rebar brought in by a forklift on the left side of the OLM
11:32am- Crane leaves again
11:33am- Pick up backs in and removed the trailer holding the plastic tank
11:55am- WATER!!!! (Low pressure test of the deluge)
1:16pm- Bunch of water over the side
1:22pm- Thar she blows
1:35pm- How hot is it in Boca Chica? Concrete is already dry again.
1:50pm- Workers start returning
2:12pm- Large group returns. They spread out and start inspecting. No one seems concerned.
(Thank you kind redditor for the gold)
2:18pm- Yellow tape strung around the outside of the OLM. People still walking around on the plate
2:43pm- Forklift brings in a caterpillar air compressor
2:51pm- A lot more people on top of the OLM than normal
3:20pm- Workers back up at the stabilizer arm on the right chopstick
3:31pm- Wood forms coming in for the pad over the deluge pipes
3:35pm- Workers on the tower at the chopsticks
3:41pm- Forklift brings in what looks like a metal strip to the center of the OLM
3:47pm- Group of VIPs arrive at the OLM
3:56pm- VIP’s leave after standing and looking up at the OLM
4:19pm- Forklift brings in another piece of metal to the left side of the OLM
4:27pm- Using a good old shop vac to clean up some of the water under the area where the forklift is waiting to put down the new piece of metal. Which begs the question, Was the missing top strip of that manifold not completely welded shut and that’s why it threw water so much further than the other parts of the plate? Or was that because it has its own dedicated water supply line and the other 2 share?
5:36pm- Forklift takes another piece of metal under the right side of the OLM
6:48pm- Forklift brings another piece of metal to under the left side of OLM
8:05pm- Crane lifts piece of pipe off of the top of the OLM. (The crane came in, extended, lifted that piece off, went down, and left again)
9:45pm- We’ve gone from watching hundreds of loads of rebar being lifted into the pit, to hundreds of loads of concrete, to 4 guys with a shop vac and a welder.
(This gets synced)
New comment from /u/santacfan on Reddit:
Starbase live-
6:46am- Crane swings over to the OLM in the first sign of life today.
7:01am- Basket removed after spending all day yesterday on the OLM
7:27am- Basket goes back into the center of the OLM
7:36am- Earthwork gets back underway on the left side of the OLM
8:01am- Piece of metal pipe with a triangular brace removed from the top of the OLM
8:34am- Another piece of pipe removed
9:30am- Basket removed
9:49am- Another piece of pipe lowered from the OLM
10:00am- Small silver tank being rolled out to the launch site. Looks like a vertically mounted tank
10:39am- Basket goes back into the center of the OLM
10:48am- 4th piece of pipe lifted out
11:16am- 5th piece of pipe
11:29am- 6th piece of pipe
2:15om- Load spreader has been attached to new tank and Grover has it under tension
2:25pm- Second crane hooked to tank to help turn it vertical
2:27pm- Tank lifted and flipped vertical
2:29pm- 2nd crane disconnected
2:32pm- Tank swung over and lowered
3:03pm- Crews back up working on the draw works shed
4:00pm- Grover disconnected
4:45pm- Long straight rebar lifted towards back of OLM
5:19pm- Clamp leveling rig lifted off of the OLM
6:49pm- Something is lifted off of the OLM. Can only see on wide shot so can’t tell what
7:04pm- Piece of metal shielding lifted up to the OLM
7:15pm- Another piece lifted up
7:19pm- 3rd piece lifted
7:58pm- New draw works shielding going up
9:21pm- Crane in front of OLM leaves
10:11pm- 2nd piece of the new draw works shielding goes up
10:23pm- Concrete pump truck goes up between the OLM and OLT. Maybe filling in that gap by the smaller manifold you see on RGV’s photos? We did see rebar lifted back that way earlier.
10:29pm- Forklift removes big United rentals piece of equipment
10:37pm- United rentals generator is towed away. (The crane had to move when it was delivered so will it come back now?)
Rover 1-
18:15pm- Sheriff arrives at production site
19:53- Sheriff left, came back, and left again
Rover 2-
20:44:16- Announcement- Attention at the orbital pad. Manual bleeding of the flame deflector plate is beginning, Manual bleeding of the flame deflector plate is beginning. This will take approximately one hour.
(This gets synced)
New comment from /u/santacfan on Reddit:
Starbase Live-
(Tornado= Raptor QD Spin up test)
11:21:21pm- Tornado
11:35pm- Small (No tornado)
11:40:45pm- Tornado
11:55:13pm- Small (No tornado)
12:08:19am- Tornado
12:31:14am- Tornado
1:01:04am- Tornado
1:16:54am- Small (No tornado)
1:19:37am- Tornado
1:52:47am- Tornado
1:55am- Depress vent?
3:56am- Workers back at pad
8:50am- Crane lifts a bunch of boards out from beside the OLM
9:15am- Basket goes up. Center
9:33am- Crane lifts something with a lot of cables hanging off of it
5:25pm- Lots of people working on top of the OLM but the cranes and lifts have been silent today
6:00pm- Intermittent closure starts. NSF in SBL chat says that Jack is reporting sheriffs at the launch site. So maybe more testing instead of something moving?
6:20pm- Pope stack is venting (Going back and looking, I’m pretty sure it was just the pope stack and not the OLM like people were saying)
7:00pm- Seems like a full test/purge of the cryo lines
7:08pm- Can’t tell if that’s the new purge line or if there is just a massive leak
7:20pm- Launch site cloaking device engaged
7:29:10- People were reporting a bang. I can hear a slight pop but NSF’s mic is so far away that I don’t know if I’d put much faith in it being anything.
7:30pm- Venting seems to be letting up some
7:34pm- Pope stack is going again
8:00pm- Still venting. Seems to die off some and then pick back up
8:30:42- Sounds like a cell phone ringing. So I think you have to discount all of the bangs and pops
9:28:53- Drone comes out of lox cloud
10:36pm- Really starting to die off. Tank finally getting empty?
10:53pm- Down to a trickle at the beach but still a significant cloud by the actual tanks
11:16pm- Vent still going but small enough for people to return to the pad and people to leave the beach
Rover 2-
20:43:40- Something is definitely wrong. 4 person red team shows up in 2 carts and makes their plans on how they are going to punch thru and get to the big lox tank and spin the shutoff valve. Stick together and get out if the monitor goes off. The banging and popping sounds like a warning klaxon on here.
21:08- One guy walks out and a pick up shows up
21:10- Pick up leaves the pad
21:12- 2 more guys walk out on their cell phones
21:32- 47 minutes later, I’m going to guess they couldn’t get the valve to shut.
21:51- Lots of honking. It seems people are trapped on the beach.
21:54- Lab switches R2’s feed to R3 and we lose the microphone
(This gets synced)
New comment from /u/santacfan on Reddit:
Starbase live-
12:48am- Concrete pump truck goes up to right of OLM. Looks like they may be finally pouring that little pad off to the side
4:14am- Basket comes down
4:37am- Crane lowers and leaves from in front of OLM
4:45am- Forklift brings in some kind of united rentals equipment
4:55am- Pick up backs in a giant generator in front of OLM
5:06am- Forklift brings in another united rentals piece of equipment
5:15am- Crane comes back. Looks it just left to make room for the deliveries
7:50am- SPMT headed to the launch site
7:58am- 3rd segment of the 4th floor of the new mega bay lifted
8:20am- Pump truck folding up, concrete truck is backed up to the OLM though so pour continues, Grover removing it’s counterweights (so that’s what the SPMT was for)
8:56am- New crossbeam test fitted at the draw works shed
8:58am- Concrete truck is gone, looks like the pour is over
9:03am- Crossbeam installed
9:11am- Pump truck goes up around the deluge tank farm (can be seen much clearer on Rover 2)
9:24am- More concrete trucks arriving, go to the pump truck
10:13am- Equipment lifted off of the OLM
10:19am- New upper crossbeam installed on the draw works shed
10:27am- Another pump truck goes up between the OLM and OLT
11:00am- Lifts are up at the oxygen and methane tank access hatches of S25
11:51am- Pump truck between OLM and OLT folds up
1:46pm- Crane lifts triangular object to top of OLM
1:54pm- Crane lifts section of pipe to top of OLM
2:04pm- Pump truck at the backside of the OLT goes down
2:30pm- Pad seems to be clearing
2:41pm- BQD hood opens (We are 40 minutes into the intermittent closure)
2:48pm- BQD hood closes
2:54pm- BQD hood opens again
3:01pm- BQD hood closes (Did they clear the OLM area just for hood tests?)
3:37pm- Quick check of Rover 1 shows test tank 24.2 sitting quietly with no SPMT’s in sight. Doesn’t look like it’s going anywhere during this closure
4:13pm- Tweet from Jack- Just got shooed out of the dunes by a drone with a speaker on it because im “in the blast danger area for today’s test”. That’s a first. 🤔 @NASASpaceflight
4:18pm- Still 2 lifts up at S25’s methane tank. Waiting on them to get done?
4:51pm- Drone
5:03pm- Last lift at S25 is going down
5:21pm- Purge of the new water line at the OTF?
6:20pm- Venting sounds but lifts are back up at S25
8:01pm- People back at the OLM and lift at the stabilizer arm on the right chopstick
(This gets synced)
New comment from /u/santacfan on Reddit:
Starbase Live-
11:50pm- Lift goes up to chopsticks. Work continues on the stabilizer arms
1:23am- Blue box looking piece of equipment that was lifted to the top of OLM yesterday is brought back down
2:33am- Concrete pump truck goes up and extends between OLM and OLT
3:28am- Tarp goes up at the draw works shed. Sparks fly. It looks like some of the cross beams are being removed
8:15am- The boom on the concrete pumper has not moved since it was set up
8:36am- Big section of black tarp set up at the base of the OLM
9:01am-Boom on the concrete pumper retracts some
9:36am- Zoom in on the end of the pump truck boom shows it in the deluge pipe pit
10:10am- Pumper truck retracts
10:16am- Workers back up at the damaged water tank shell. Yeah the tank doesn’t exactly sit flush with the straight edge they hold up
10:28am- Pumper truck extends back out
10:35am- Basket goes up too top left side
12:34pm- Pump boom is all the way over by the 3rd manifold. They may be finishing up the concrete under the OLM.
12:50pm- Back up working on the stabilizer arms
1:50pm- Pump truck folds up
2:10pm- New crossbeam is being risen to the draw works shed
3:02pm- You can see all 3 access hatches on S25 have been opened
4:09pm-Zoomed in shot shows that the concrete is up to the top of the wooden forms around the OLM
4:25pm- It looks like they may have back filled over the deluge feed pipes and now they’re just trying to work on the correct grade
4:57pm- Forklift brings in what looks like a giant toy top to a work station set up by the OLT
5:32pm- Forklift removes some large hoses from same work station
6:11pm- Forklift lifts a circular hatch. Moves it to the other side of the OLT
6:35pm- 3 lifts up at the access hatch to S25’s methane tank
7:30pm- Upper cross brace removed from the draw works shed
7:53pm- Cutting torch comes out at the shed
8:58pm- Sparks flying, welders welding. Slow day for cranes and lifts but no doubt lots of work is still getting done.
(This gets synced)
New comment from /u/santacfan on Reddit:
Starbase live-
12:36am- Lift goes up to the stabilizer arm again
12:47am- Lift goes down
1:26am- Lift back up at the draw works shed. Sparks flying
2:02am- Lift go up to S25
2:43am- Lift at S25 goes down
3:47am- Lift at the draw works goes down. About half done.
5:20am- Pump truck folds up. Pour done
6:54am- Lift back up at the draw works shed
8:08am- Lift goes back down. About 3/4 done.
8:11am- New medium lift crane arrives at the right side of OLM
8:18am- Lift back up at S25 and right back down after a few minutes
8:53am- Piece of equipment lifted to the top of the OLM. (Blue, boxed shape, not quite sure what it was)
9:06am- Lift goes back up to the draw works
9:13am- Another piece of equipment is lifted to the bottom of the Cryo pipe leg.
9:47am- 2 lifts go up to S25
9:55am- Small rectangular piece of metal lifted to the top of the OLM
10:14am- Piece of metal that was just lifted is removed
10:21am- Lift at the draw works goes down
10:31am- Lift goes back up
10:32am- Piece of metal goes back up. Needed some fine tuning?
10:41am- Similar shaped piece gets lifted up
10:55am- 3rd piece of metal goes up
11:15am- Piece of pipe lifted up to the new door
11:34am- Another piece of pipe goes up
11:42am- Lifts go down at S25
11:58am- Lift at the draw works goes down
12:16pm- Lift goes back up at S25
1:16pm- Lift goes back up to the draw works shed
3:30pm- Short piece of metal beam lifted to the top of the OLM.
3:57pm- Basket goes up to the new door
4:05pm- Basket goes down
4:41pm- Lift at the draw works shed goes down. Looks like all of the damaged siding is now removed. (Took a total of 9 hours and 44 minutes to remove it)
5:26pm- Forklift lowers sheet of metal into the deluge feed pipe pit
7:24pm- Purge of the deluge pressure system
8:03pm- Lifts at S25 have gone down
8:04pm- Next mega bay section and booster stand are on the move
8:19pm- Cop at the roadblock? Stopped traffic long enough for the booster stand to move down Hwy 4 and turn on Eichorn
8:37pm- Booster stand went over for storage by the raptor install stand
8:47pm- Lifts go back up to S25
(This gets synced)
Not sure what to make of this crazy contraption: https://twitter.com/nasaspaceflight/status/1678949709661065217?s=46&t=Mj914Aam14loAYQOISZ9zQ
New comment from /u/santacfan on Reddit:
Starbase live-
11:50pm- Lift that had been up at the chopsticks goes down
11:56pm- Lift goes back up to the chopsticks
12:00am- Lift goes back down
1:48am- Lift goes back up to the chopsticks
4:11am- Lift goes back down
6:29am- Basket up top of OLM
6:45am- 2nd segment of the 4th level of the new high bay lifted
7:01am- Basket down
7:30am- Basket up to the door at the top of the new stairs
7:31am- Large L shaped metal object (I think it’s a small diameter pipe) lowered into the pit
7:40am- Basket down
7:50am- Basket up top of OLM
8:19am- 2 lifts go up to the side of S25
8:33am- Basket down
8:53am- Basket up to the door
9:26am- Basket goes down
11:03am- Large L shape pipe that was lowered earlier is repositioned
11:55am- Lift goes back up to the chopsticks
12:21pm- Zoom in on the crew working on the chopsticks. Seem to be working on the hydraulics for the stabilizer arm
12:34pm- Looks like they removed the hydraulic ram
12:44pm- Lift moves over to the other side of the stabilizer arm
1:05pm- Lifts go down at S25. Access hatch is open and vent tube installed
2:25pm- Lift back up at S25
3:38pm- Square piece of metal lifted to the top of the OLM
4:35pm- Concrete pump truck seen in background. Checked Nerdle cam and it looks like it was pouring around the high pressure tanks for the deluge earlier and now it’s over by the old landing pad.
4:40pm- Another piece of metal lifted to the top of the OLM
5:33pm- Pumper truck folds up to leave
6:12pm- Lift goes up to top of chopsticks
6:33pm- 2nd lift goes up to the stabilizer arm
6:46pm- First lift goes down
7:03pm- 1 of the lifts at S25 goes down
7:07pm- Lift at the stabilizer arm goes down. No sign of a new hydraulic piston
7:16pm- Both lifts go back up
7:25pm- Top lift goes back down. Looks like they are just inspecting
7:51pm- Lift at the stabilizer arm goes down. Was working in the piston area but SBL zoomed out and went on a tour
9:18pm- Lift goes up to the side of the drawworks shed. Whoever was hoping that they would replace the shielding soon might be in luck.
10:03pm- Lift at the drawworks goes down. There was definitely sparks flying like they were starting to cut something.
10:46pm- Lift was back at the drawworks shed. Looks like they tried a different method of cutting and then went back down
11:00pm- Concrete pump truck arrives at the right side of the cryo pipe pit. Time to finally pour it’s lid?
11:05pm- Pump unfolds
12:07pm- First concrete truck is at the pump and the arm folds out towards the far side of the cryo pipe trench. The lid it is.
(This gets synced)
New comment from /u/santacfan on Reddit:
Starbase live-
12:57am- Short piece of pipe lifted into the pit
7:27am- Rebar lifted over by the deluge area. No idea where this is going. Maybe just staging it for the OLM pit?
7:33am- More rebar lifted
7:40am- Possible metal imbed lifted
7:43am- Another imbed. Square piece of metal
7:49am- Another imbed. 90 degree angle piece
7:52am- Crane moving the rebar lowers
9:15am- Large straight rebar lifted over to the pit
9:22am- More rebar
10:26am- Crane on left side disconnects from whatever it was supporting. (Most likely the small section of pipe that was lifted in last night)
11:00am- Left crane lifts something into the pit. Can’t tell what it is
11:09am- Deluge pipe lifted over. Has to be one of the feed pipes coming in from the bunker.
11:47am- LR11000 lifts large metal frame to the ship QD. Looks like it went to the little side wing
1:09pm- More rebar lifted over
1:15pm- More rebar
1:26pm- More rebar
2:03pm- LR11000 goes for a walk
2:15pm- More rebar
2:24pm- Long reach excavator tamps down bottom of pit
2:54pm- More rebar
3:08pm- LR 11000 arrives next to S25
3:14pm- Load of scaffolding pieces lowered to the top of the OLM
3:31pm- More rebar moved
3:34pm- LR11000 picks up the squid
3:39pm- More rebar swung over
3:48pm- Squid swung over to S25
3:55pm- Lift goes up at S25
4:01pm- Workers start connecting the squid
4:22pm- Squid connected
4:23pm- Crane lowers something between OLM and OLT. Can’t see what though
4:43pm- Grover goes up in the background and moves 3 loads. Looks like the counterweight tray and 2 more counterweights
5:05pm- More rebar
5:45pm- Crane on the left side lifts deluge feed pipe and repositions it
6:20- Lift goes up at S25
6:29pm- Deluge pipe lifted out and sat by side of pit. Workers gather around the end
6:36pm- Lift at S25 goes down
6:37pm- Lift goes up to Chopsticks, near pivot point by the tower
6:43pm- Deluge pipe lifted back into the pit
6:49pm- Forklift drives under OLM
7:06pm- Appears to have another one of the plate extensions. Goes between cryo pipe leg and new stairs leg
7:39pm- Disconnected from the forklift
8:45pm- Scaffolding and tarps being set up under the OLM. The great weldathon continues.
9:15pm- Grover moves back closer to the deluge tank farm and starts lifting counterweights back on
10:02pm- Grover finishes stacking counterweights and turns towards the water deluge tank farm
(This gets synced)
Thanks, updated!
New comment from /u/santacfan on Reddit:
Starbase live-
1:54am- LR11000 disconnected from the y pipe
2:51am- Little crane lifts what appears to be a stand out of the pit
2:57am- What looks like a short piece of pipe is lifted into the pit
3:51am- Stand lowered into the pit
4:00am- LR11000 swings over and lowers it’s hook into the pit
4:39am- Grover lifts more rebar over for the cryo pit lid
4:50am- Another load of rebar is moved over
4:58am- 3rd load of rebar moved. That’s going to be one beefy lid
9:42am- Grover lifts what may be one of the extra deluge plate extensions over to the gap by the new stairs
9:59am- Swung back over to the side and sat down
10:07am- Grover lowers
11:14am- Concrete being cut
11:15am- Grover shows off and swings the extension plate back over to the OLM while lowered.
11:38am- Plate lowered. Lines go slack.
11:40am- Raised back up
11:47am- Lowered back down
11:57am- Picked back up and swung off to the side again
12:53pm- Generator removed from the pit
1:24pm- Basket goes up
1:31pm- LR11000 unhooks from whatever it was attached to (Most likely the Y pipe)
1:33pm- Basket goes down
2:07pm- Grover starts to remove it’s counter weights to move (Maybe to Masseys to lift B10?)
2:13pm- Grover removes more weights
2:18pm- More weights moved over to an SPMT
2:23pm- There goes another
2:24pm- LR11000 takes tension on its lifting straps
2:38pm- LR11000 lifts another deluge pipe. Grover removed 4 more weights
2:41pm- Pipe is raised higher and swung over OLM
2:48pm- Pipe starts lowering
2:58pm- Pipe is sat on the ground and the LR11000 is unhooked
2:59pm- Small crane hooks to the pipe
3:05pm- Pipe is swung over towards the left most manifold. So looks like it’s the left side of the Y. If the piece lifted early this morning was the right side, this should be the last piece to go around the OLM. Now we need the 2 feed pipes from the concrete bunker over.
3:05pm- At the same time, Grover lowers.
3:38pm- Grover drives away
4:43pm- The LR11000 drives away from the OLM
5:35pm- Small crane moves into the area that the LR11000 was sitting
7:34pm- Chopsticks lowered. Indicating all of the big lifts on the right side and behind the OLM are finished
8:04pm- Extension piece (?) lifted back over towards the OLM.
11:00pm- Pretty quiet evening from what we can see. I’m sure the welders are hard at work. I’ll be watching for more rebar to go in the pit to signify that they are done and the pipes are ready to be buried.
(This gets synced)
I think once it’s done it will be structural. But it needs a lot more reinforcement.